Wiring & RewiringNovember 26, 2026

Cost to Rewire a House in Ontario: Published Ranges, the Process and Timing

The cost to rewire a house comes down to what is in the walls now, how hard it is to reach, and how much of it has to come out. In Ontario the decision usually follows one of a handful of triggers: knob and tube, which the Electrical Safety Authority (ESA) dates to homes from the early 1900s to the 1940s; aluminum branch wiring from the mid-1960s to the late 1970s; an insurer asking questions; a renovation that opens the walls anyway; or a house that has simply run out of circuits.

This post walks through why homes get rewired, the ranges KV Bear Electrical publishes for the two most common whole-house jobs, what moves a quote within them, what the work involves from the ESA notification to the patching, and how long rewiring a house takes. The rules quoted come from ESA and a municipal building department, and each page is listed at the end.

Why Ontario houses get rewired

Knob and tube is the oldest case. ESA's Flash 25-05-FL says the 2021 edition of the Ontario Electrical Safety Code deleted the rules for installing it, but ESA is clear that the Code is not retroactive. Concealed runs feeding lighting and receptacle circuits may stay in service while they are protected at 15 A, have not been overloaded with added outlets, and look sound where you can see them. The push to replace it tends to come from insurers: ESA says many will not provide or renew coverage on these homes, and some require the wiring to be replaced before they will.

Aluminum branch wiring is the second. ESA says a house built between the mid-1960s and the late 1970s may have it, and that the Code still permits aluminum wiring. Trouble shows up at the terminations, because aluminum oxidizes and does not suit devices designed only for copper. Many owners fix those connection points and stop there, but ESA's Flash 25-18-FL notes that some insurers require the aluminum to be replaced with copper.

Capacity is the third. The same knob and tube flash says these homes may not have the electrical capacity for today's needs, and it lists what modern wiring adds: more circuits, splices made inside approved boxes, dedicated circuits for certain appliances, grounded and bonded devices, tamper-resistant receptacles, ground fault protection in bathrooms and outdoors, and arc fault protection on receptacle circuits. A kitchen or basement renovation is often when owners decide to deal with the rest of the house, since wiring run through open framing avoids most of the cutting and patching.

Rewire house cost: the published ranges

KV Bear Electrical publishes two whole-house figures (as of November 2026). Replacing aluminum wiring with copper in a typical 3-bedroom Ontario home runs $8,000 to $15,000 or more, and the figure moves mainly with how easy the wiring is to reach and how complex the layout is. Full knob and tube removal in a typical Ontario home runs $8,000 to $20,000 or more, set by the size of the home, access to the walls and ceilings, and how much knob and tube is still in use. Houses with only partial knob and tube usually land toward the low end of that one.

These are published ranges, not quotes. A rewire is priced after an assessment, because two houses of the same size can hide very different amounts of old wiring. For comparison, the narrower repair many aluminum-wired homes choose, pigtailing each connection with copper, is published at $2,000 to $4,500 for a typical 3-bedroom home, depending on how many connection points there are.

Have electrical work in mind? Get a free quote.

Licensed & Insured | ECRA/ESA 7014730

What moves the cost to rewire a house

The published ranges already name the main variables. In a real house, they show up like this.

Access comes first. In an unfinished basement or an open attic, new cable can run along the framing with little damage. Finished ceilings, plaster walls and extra storeys mean more fishing, more small openings and more patching afterward.

Then there is how much old wiring is still live. A house whose kitchen and basement were redone in copper years ago may only need the original bedroom and living room circuits replaced, and ESA notes that some homes have a mix of aluminum and copper. An untouched house needs every circuit done.

The panel is often part of the conversation, because new circuits need breakers to land on. KV Bear's panel upgrade page publishes $2,500 to $5,000 for a typical 100 to 200 amp upgrade (as of November 2026), and that work is shown as its own line on the quote.

Additions matter too. A rewire is a natural time to add circuits for a kitchen, a home office, an EV charger or outdoor lighting, and each one is listed separately rather than buried in the total. Finally, ask whether drywall patching is included and to what finish, so every quote you compare covers the same work.

What rewiring a house involves, step by step

It starts with an assessment. ESA recommends having a Licensed Electrical Contractor assess a house with knob and tube, and points out that this differs from a home inspection because it looks only at the electrical system. For aluminum, ESA says each home is different and has to be assessed on its own. A contractor can also carry out an Electrical System Safety Assessment, which ESA describes as a review of the wiring and devices for hazards that could lead to a fire or a shock.

Next comes the notification. ESA says almost all electrical work has to be reported, and that the person doing it should file before the work starts. Bulletin 2-3-19 also leaves aluminum and ungrounded wiring such as knob and tube out of the homeowner exemption for swapping fixtures and switches, so changes on those circuits are filed too.

The new cable then goes in through small openings in walls and ceilings, and boxes are set. ESA's rough-in inspection happens once the branch circuit wiring and outlet boxes are installed and before insulation, vapour barrier or drywall hides them, and no wiring may be concealed until an inspector authorizes it. That is why patching comes near the end.

If the panel or the service is replaced, the utility disconnects the power, and the new equipment has to pass ESA's service inspection before ESA authorizes the utility to energize it again. When everything passes, ESA issues a Certificate of Acceptance to whoever filed the notification. Keep a copy for your insurer and for an eventual sale.

Building permits are a separate question. ESA reminds homeowners that a building permit and an electrical notification are different, and that a project may need both. The City of Vaughan, for one, lists electrical projects among the work that generally does not need a City building permit, because ESA inspects them. If the rewire is part of a bigger renovation, check what your municipality requires for the rest of the work.

How long does it take to rewire a house?

KV Bear's knob and tube service page gives one figure: a full removal and rewire typically takes 3 to 7 days, depending on the size and complexity of the home, and you get a timeline at the assessment. The aluminum wiring page gives no duration, so this post does not quote one for aluminum replacement.

What stretches or shortens the schedule is fairly predictable. If you are living in the house, circuits come off and go back on in sequence, and furniture has to move away from the walls being opened. The rough-in inspection has to fit between running the cable and closing the openings. A panel change adds a utility disconnection and reconnection. Plaster, finished ceilings and a third storey all slow the fishing of new cable. Ask for a timeline built around your own house, in writing, along with the quote.

House rewiring or a narrower repair

Not every house needs everything replaced. For aluminum, ESA allows repairs at the terminations with devices marked for aluminum, or with copper pigtails joined by marked connectors, and many owners go no further unless their insurer asks for copper. For knob and tube, removing only the circuits still in use can be enough where modern wiring covers the rest, as long as the insurer accepts it. A full rewire makes the most sense when the insurer requires it, when most of the original wiring is still live, or when a renovation will open most of the walls anyway.

Before you choose, ask your insurer what it requires and keep its answer on file. Then compare quotes on the same scope: which circuits are replaced, whether the panel is included, whether patching is included, and who files with ESA. KV Bear Electrical (ECRA/ESA 7014730) assesses older homes and provides written, itemized quotes for rewiring. Call 905-999-5048 to book an assessment.

Frequently Asked Questions

Does rewiring a whole house need an ESA notification?

Yes. ESA says almost all electrical work has to be reported, and the person doing it should file before starting. A Licensed Electrical Contractor files for you; if you rewire your own home, you file it yourself. ESA issues a Certificate of Acceptance once the work passes.

Can a relative or handyman help me rewire my house?

No. ESA's do-it-yourself rules let only the homeowner, after filing a notification, or a Licensed Electrical Contractor do electrical work in a home. Those rules bar a relative, a friend or a neighbour from doing the work on your behalf, however handy they are.

Is knob and tube wiring illegal in Ontario?

No. The 2021 Code removed the rules for installing it, but ESA says the Code is not retroactive, and existing concealed runs may stay on 15 A protection if they have not been overloaded and look sound. Insurers set their own conditions, and many want it replaced.

How much does it cost to rewire a 3-bedroom house?

For aluminum replacement, KV Bear's published range for a typical 3-bedroom Ontario home is $8,000 to $15,000 or more (as of November 2026). Knob and tube removal in a typical home is published at $8,000 to $20,000 or more. Your own quote follows an assessment of access and how much old wiring remains.

Do the walls have to be opened to rewire a house?

Some, yes. New cable is fished through small openings in the walls and ceilings, or run along open framing where possible, and those openings stay open until ESA's rough-in inspection. Ask whether patching is included in the quote.

Published by KV Bear Electrical

KV Bear Electrical Inc. is a licensed residential electrical contractor (ECRA/ESA 7014730) based in Oshawa, Ontario. The facts here come from the official sources listed above. Have a question about your home? Call 905-999-5048.

Have a Question? Get a Free Quote

ECRA/ESA 7014730 | Licensed & Insured

Get Your Free Quote Today

Prefer to talk? Call us.

By submitting this form, you agree to receive email from KV Bear Electrical about your request. You can ask us to stop at any time.